Pilot Study Demonstrates Benefits Of Pipeline Inspection And Risk Assessment
By David Jones, Stephen Peet & Luis Espinosa, Pipeline Integrity International
Group Limited, England, and Adrian Espinoza, Pemex E&P, Southern Region, Mexico
Throughout the world, pipeline companieslarge and smallare conducting pipeline
inspections and risk management assessments. Their objectives are to ensure the safety of
the public and the environment. Mexicos Pemex E&P (PEP), Southern Region, that
operates 7,320 miles of crude oil and gas transmission lines, has been carrying out
pipeline risk evaluation work on its pipeline systems for several years.
PEP contracted Pipeline Intergrity International (PII) to conduct a pilot study and
rehabilitate 90 miles of crude oil and gas pipelines operated by PEP. The six lines
selected for the pilot study had an in-service life ranging from 2- to 36 years. Other
pertinent pipeline details are summarized in Figure 1.
To determine the current condition of the six pipelines, intelligent pig inspections were
conducted from 1996 to 1997. PIIs high resolution magnetic flux leakage (MFL)
inspection tool, was used for finding and sizing corrosion and other metal loss defects.
Fitness-For-Purpose (FFP) Assessment
Subsequently, a Fitness-For-Purpose (FFP) assessment was conducted as the basis for
recommending an appropriate rehabilitation strategy, including pipeline coating repairs
and scheduling appropriate re-inspection intervals of the respective pipelines. An
additional part of the study involved a qualitative risk assessment to prioritize the
future maintenance activities of the pipelines.
Included in the assessment data were the dimensions of any feature detected by the
inspection to the actual pipeline operating conditions. This allowed the identification of
any features that required immediate repair. It also provided a strategy to determine the
long-term integrity of the pipelines.
Findings
The inspections reported internal and external corrosion, manufacturing defects, dents and
girth weld anomalies (Figure 2).
The inspections were typically conducted 18 months prior to the FFP. The first stage of
the FFP was to estimate maximum conceivable corrosion rates, following the inspection, as
the basis for estimating the current dimensions of the corrosion and the need for
immediate repairs.
On this basis, 13 (12 external and one internal) corrosion features were found to require
immediate investigation to confirm their current dimensions as the basis for a repair
decision (Figure 3).
It should be noted that appropriate assessment methods were utilized to avoid unnecessary
repairs. For example, under the published ANSI/ASME B31.G guidelines, 407 pipeline repairs
were required immediately following the inspections (Figure 4).
All of the manufacturing defects detected were found to be insignificant. However, two
dents (associated with metal loss defects) and one girth weld anomaly required immediate
excavation as the basis for a repair decision.
The next stage was to consider the longer-term integrity of the pipelines, taking into
account further corrosion growth (Figure 5). The strategy was to determine optimal
re-inspection intervals to allow actual corrosion rates to be determined as the basis for
defining further rehabilitation. The intervals were (i) based on estimated future maximum
corrosion rates and (ii) devised to ensure that (theoretically) only a few
(32) coating repairs to external corrosion and (3) pipeline repairs to internal corrosion
would be required before the lines were scheduled for re-inspection. It should be
emphasised that re-inspection intervals have been individually determined for each
pipeline and range from 5 to 10 years after the previous inspection.
Palomas to Cangrejera Pipeline
In looking at the pipeline results, the 3.6-mile, 24-inch diameter Palomas to Cangrejera
crude oil pipeline was inspected by PII on June 12, 1997. The 1.8 mile Palomas to Nuero
Tampa section entered service in 1995. The 1.8-mile Nuevo Teapa to Cangrejera section was
placed into service in 1995 and the Nuevo to Cangrejera section, also measuring 1.8-miles
in length, entered service in 1978. The pipeline is constructed from X35 pipe,
predominantly of 12.7mm wall thickness, and currently operates at a pressure of 8 bar.
The inspection report identified:
(i) 4,329 external corrosion features (563 in the
Palomas to Nuevo Teapa section and 3,766 in the Nuevo Teapa to Cangrejera section),
(ii) 1,890 internal corrosion features (1495 in the
Palomas to Nuevo Teapa section and 395 in the Nuevo Teapa to Cangrejera section), and
(iii) 579 manufacturing defects (542 in the Palomas to Nuevo Teapa section and 37 in the
Nuevo Teapa to Cangrejera section).
The number and depths of the reported external corrosion features found in the Paloma to
Neuve Teapa section was not considered to be consistent with a pipeline that had only been
in service for two years (at the time of the inspection). Furthermore, the pipeline
section (which entered service in 1997) was found to contain significantly more
manufacturing defects (112/mile) than the Nuevo to Cangrejera section, which entered
service in 1978. Modern pipe produced circa. 1995 would be expected to contain
significantly fewer manufacturing defects than pipe produced circa. 1978. It was therefore
concluded that the pipeline was very likely constructed from old pipe
containing corrosion.
Consequently the external corrosion in this section is anticipated to be in an
inactivestate. However, the study recommended that the nine deepest reported features be
investigated to provide confirmation (e.g. to confirm that the old pipe has
been re-coated as required by ANSI/ASME B31.4) that the external corrosion was
pre-serviced and is now inactive.
Although the study assumed that the internal corrosion mechanism in this section was
active (the Nuevo to Cangrejera section contains internal corrosion), the extent to which
the corrosion was pre-service or occurred in-service could not be determined. A repair
schedule was devised to ensure the pipeline integrity based on a maximum conceivable
future corrosion rate. The number of repairs was shown to increase significantly after
July 1999.
Nuevo Teapa to Cangrejera Section
At the time of the inspection, this section of the pipeline had been in-service for
approximately 20 years and the extent of the corrosion (external and internal) was found
consistent with pipe of this age. It was assumed that both corrosion mechanisms were still
active and a repair/re-coating schedule for the external corrosion (three that were
immediate) was devised. No repairs of any internal corrosion features were found to be
required before 2015.
Consequently it is recommended that the pipeline be re-inspected before this date.
Furthermore, in the period before the inspection, PEP was advised to monitor the condition
of the external coating, efficiency of the CP system, monitor product chemistry and to
utilized suitable corrosion inhibitors. After the re-inspection, actual corrosion rates
should be determined and the future rehabilitation determined.
Dents
Two dents were reported by the inspection (one plain and one associated with metal loss).
In the study plan, plain dents are defined as smooth dents not associated with welds or
metal loss. Plain dents with a depth of £ 7% of the pipe diameter are considered as
insignificant at a hoop stress of 72% SMYS in the absence of significant pressure cycling.
Dents associated with defects are the severest form of pipeline damage. Cracks associated
with gouges or weld toes in dents can record very low failure pressure. The reported dent
identified is of a depth less than 5 percent of the diameter, the operating stress level 8
percent SMYS, and there is no significant pressure cycling. Therefore the dent is
considered insignificant in relation to the integrity of the pipeline.
Conversely, the dent associated with the metal loss was located at the top of the pipe and
is therefore likely to have occurred after the line was placed in service. The study
considered it conceivable that there could be cracking associated with this defect. PEP
was therefore advised to investigate this defect to confirm the extent of any damage and
make a repair decision.
The inspection also detected a girth weld anomaly whose signal is characteristic of a
crack-like defect. Therefore it is recommended that the defect be excavated and the crack
confirmed and repaired with epoxy filled shell.
Risk Assessment
A study was also conducted to prioritize the future maintenance of the six pipelines.
The aim is to identify the greatest damage/defect risk to a pipeline that allows the
selection of an appropriate maintenance (monitoring/inspection) method to reduce the risk.
An accepted method for determining which maintenance technique to use on a pipeline is a
Prioritization Scheme. These types of schemes are increasingly being used to
guide operators on the optimum use of maintenance methods. For example, if a
pipelines major cause of damage is third party interference, increased surveillance
would be appropriate. However, if a pipeline is at greatest risk from internal or external
corrosion, then an inspection using an intelligent pig would be appropriate.
The prioritization scheme considers the probability and consequences of failure within a
group of pipelines (or sections of a single pipeline) by systematically assessing the
pipelines design, operation and failure history and allocating points. High points
are awarded to high risk (Figure 6). For example, the probability of failure due to
external corrosion is evaluated by considering the quality of the pipe coating, the
effectiveness of the CP system, the soil condition, the operating stress of the pipeline,
etc. The consequences of failure are considered by estimating the density of the
surrounding population, the volume of product released, the risk to the population and
surrounding buildings, the security of supply and environmental impact.
- By customizing the scheme to a group or section of a
pipeline can result in the following advantages:
- Rank all pipelines within a group (or sections of a
pipeline) in terms of probability of failure and the consequences of failure,
- Determine which pipeline (or section of a pipeline) is
most in need of some type of maintenance measure, i.e. identify hot-spots of
risk, and
- Identify the most appropriate maintenance measure to use.
In this case, PIIs PC software based ASIRE ( A System for Pipeline Risk Evaluation)
was applied, following the inspections, to prioritize the six pipelines in terms of total
risk. Figure 7 presents the relative risk of the six PEP pipelines, while Figure 8 shows
the failure index for the Cunduancan to Dos Bocas pipeline. The failure index also shows
the Cunduancan to Dos Bocas at much most risk from sabotage/pilferage, and increased
surveillance is recommended, Although the study assumed that the internal corrosion
mechanism in this section was active (the Nuevo to Cangrejera section contains internal
corrosion), the extent to which the corrosion was pre-service or occurred in-service could
not be determined. A repair schedule was devised to ensure the pipeline integrity based on
a maximum conceivable future corrosion rate. The number of repairs was shown to increase
significantly after July 1999.
Conclusions
To date the assessment of five of the six pipelines has been completed. In particular,
utilizing appropriate assessment methods, 13 corrosion features require investigation to
ensure their immediate integrity; the published guidance (ANSI/ASME B31.G) requires 407
pipeline repairs immediately after the inspections (i.e. 18 months ago).
To ensure the longer-term integrity, individual re-inspection intervals (5 to 10 years)
have been defined for each pipeline. Before the re-inspections, 32 coating repairs and
three pipeline repairs of internal corrosion are required and the timing has been defined.
Following the re-inspections, actual corrosion rates should be determined as the basis for
defining further cost-effective rehabilitation.
Finally, the risk assessment has prioritized the six pipelines for future maintenance
activities. Currently the Cunduancan to Dos Bocas is most at risk from sabotage/pilferage
and increased surveillance is recommended. P&GJ
This article is based on a technical paper originally presented by the
authors.
|