Down Deep in Durango
After the breakthrough, BTrenchless grouted the exterior annular space around the 48 inch steel casing and then skidded the 36 inch diameter PVC carrier pipe into the tunnel. The interior annular space was then grouted as the final step to complete the tunnels.
As of early April 2009, the SBU M was on the surface and being readied to bore the 130-foot long upper tunnel. The second tunnel is at an offset angle to the lower and will break through into the shaft approximately 60 feet from the top of the shaft. BTrenchless anticipates the second launch will occur in mid April.
BTrenchless, a division of BT Construction, Inc. located in Henderson, CO, has been in business for more than 25 years. During this timeBTrenchless has completed numerous projects in Colorado and the Western United States includingmicrotunneling, tunnel boring, pipe jacking, guided auger boring, auger boring, pipe ramming, horizontal directional drilling, pipe bursting, sliplining and potholing.
EPC Corporation of Glendale, AZ, is a construction company offering general contracting, design/build, and construction management services. EPC specializes in commercial/industrial building, heavy/highway construction, utility construction, industrial maintenance, water/wastewater plants, correctional institutions, and power plants.
The LPWWA’s project is being managed by Bikis Water Consultants LLC. The approximately $6 million project to distribute water from the new lake has been funded by the following sponsor entities: Animas La Plata Water Conservancy District, Southwestern Water Conservation District, Colorado Water Conservation Board Ute Mountain Ute Tribe, Southern Ute Indian Tribe, and the Colorado Water Resource and Power Development Authority.
FOR MORE INFORMATION:
BTrenchless, (303) 286 0202
EPC Corporation, (623) 934-0225, www.epccorp.net
Robbins TBM, (440) 248-3303, www.robbinstbm.com